Costs trades pass on

  • Materials bought for the job: cable, timber, fixings, plasterboard, sanitaryware.
  • Plant and tools hired for the job, such as access towers, mini diggers and skips.
  • Fuel and consumables used on site.
  • Prefabricated items made off site.
  • Work by other trades you engaged, on cost-plus or day-work jobs.

Why the receipts matter under CIS

In the UK’s Construction Industry Scheme, the main contractor deducts tax from a subcontractor’s payment, but not from the whole amount. It first takes off what the subcontractor paid for VAT, consumable stores, fuel (except for travelling), plant hired for the job, prefabricated materials, and materials it bought directly.

The contractor can ask for evidence, such as receipts, that the subcontractor paid for materials directly. Without it, the contractor estimates the cost of the materials, and an estimate that is too low means more tax taken from your payment. HMRC defines the cost as what the subcontractor can show it paid for materials used on that contract.

Reverse charge on the invoice

Since 1 March 2021, most standard-rated and reduced-rated building work supplied between businesses registered for both VAT and CIS falls under the domestic reverse charge. The invoice must say the reverse charge applies (for example “Customer to pay the VAT to HMRC”) and must not add the VAT to the amount the customer pays. HMRC lists the exclusions, including customers who tell you in writing that they are end users.

Cost-reimbursable contracts

On NEC4 cost-reimbursable options, the contractor is paid its Defined Cost, and its records are open to the project manager. Monthly applications come with cost reports that point to delivery notes or invoices. In England, Wales and Scotland, the Construction Act requires a payment notice to state the sum due and how it was worked out.

Either way, the client compares each charge with a supplier’s document. Send them together.

In Xero

Record each merchant or hire invoice as a bill, or a card purchase as spend money, with the receipt attached. Assign it to the customer as a billable expense. A tracking category for each site or job keeps costs apart when one contractor gives you several jobs.

Worked example

Fictional example

An electrical subcontractor in England invoices a main contractor for first-fix work on an office refurbishment, which is standard-rated. Both are registered for VAT and CIS, and neither is an end user, so the reverse charge applies.

Invoice INV-2041 · Northgate Build LtdSample data
Invoice lineReceipt in the packAmount
Labour, first fix, 8 daysSigned day sheets£3,200.00
Cable and fittingsWholesaler invoice£842.15
Consumer units (6)Wholesaler invoice£468.00
Access tower hire, 1 weekHire company invoice£135.00
Total (excluding VAT; reverse charge applies)£4,645.15

The pack puts the invoice first and the two wholesaler invoices and the hire invoice behind it. The contractor can match £1,445.15 of materials and plant to receipts and take the CIS deduction from the £3,200 of labour only.

Every invoice with its receipts.

AllAttached builds one PDF per Xero invoice: the invoice first, then the receipts behind each charge.